Lab / Buildability

Steel Assembly Planner

Turn a member schedule into transportable and liftable assemblies, then compare warnings, site work and rough cost.

Scenario status1 fail
Total steel67.30 t
Max lift use118%
Rough cost£108,538

Step 1

Member schedule

6 rows

10,656 kg10.656 t
10,656 kg10.656 t
10,598.4 kg10.598 t
19,468.8 kg19.469 t
12,480 kg12.480 t
3,440 kg3.440 t

Step 2

Assembly split

3 options in current scenario

Review
Unit weight4.28 t
Lift weight4.71 t
Payload/load4.28 t
Cost£79,224
Length18 m within standard length
Width2.8 m within width limit
Height3.2 m within height limit
Payload4.3 t per load
Lift4.7 t at 14 m radius
Review
Unit weight3.12 t
Lift weight3.43 t
Payload/load3.12 t
Cost£23,096
Length18 m within standard length
Width5.8 m likely needs escort
Height3.4 m within height limit
Payload3.1 t per load
Lift3.4 t at 12 m radius
Fail
Unit weight3.44 t
Lift weight3.78 t
Payload/load3.44 t
Cost£6,218
Length4 m within standard length
Width2.4 m within width limit
Height2.4 m within height limit
Payload3.4 t per load
Lift3.8 t lift exceeds usable 3.2 t